Customer

AEP

Location

Oklahoma

Highlights

  • Identified on-site engineering discrepancy before construction
  • Resolved issue rapidly to meet project deadlines
  • Saved significant time and money for AEP

Preventing Critical Cable Installation Errors for AEP 

The Challenge

During the substation construction review for AEP, our team discovered a misalignment between the raceway plan and the cable schedule, putting the project’s installation accuracy and timeline at risk. 

The Solution

Upon identification of the error, Think Power’s project lead promptly coordinated with AEP’s engineering team. We discovered we were working with an outdated cable schedule. Thanks to our streamlined collaboration and experience, the correct schedule was provided quickly, ensuring a seamless transition to updated plans and avoiding installation mistakes. 

Key Benefits

  • Experienced oversight prevented cost overruns and schedule delays. 
  • Accurate coordination with stakeholders minimized risk of change orders. 
  • Customer-focused response protected AEP’s investment and critical milestones. 

The Results

Think Power Solutions' proactive approach prevented incorrect cable installations and kept construction on schedule for AEP. By identifying issues early and collaborating effectively, we helped AEP avoid expensive change orders and ensured project delivery on time and within budget. 