Customer
SPEC
Location
Texas
Highlights
-
Easement Coordination Across Multiple Landowners
-
Efficient Staking Across Challenging Terrain
-
Trusted Execution Backed by Long-Term Client Relationship
Streamlining Voltage Conversion Through Stakeholder Coordination and Field Expertise
The Challenge
Root Cause Analysis
- Multiple Stakeholders: Coordinating with dozens of landowners required advanced planning and strong communication.
- Environmental Barriers: Thick vegetation and uneven ground slowed traditional fieldwork.
- No Fixed Timelines: The absence of a hard deadline meant proactive progress tracking was essential.
The Solution
Stakeholder-Centered Approach
The Think Power Solutions team leveraged time management tools and relationship-building techniques to efficiently communicate with landowners and facilitate the approval process for reroutes and easements.Field-Based Problem Solving
Despite variable terrain, the staking team maintained accuracy using local knowledge and consistent on-the-ground updates, ensuring design and fieldwork aligned throughout.Utility Integration
Fieldwork was conducted in sync with the client’s broader capital improvements to minimize rework and align with construction readiness milestones.Key Benefits
- Time Savings: Accelerated routing and easement acquisition through field-first strategy.
- Improved Access: Maintained project pacing despite environmental obstacles.
- Client Satisfaction: Reinforced long-standing trust with SPEC through clear execution.
- Construction-Ready Delivery: Completed all pre-build milestones, allowing the voltage conversion to progress.