Customer
PEC
Location
Texas
Highlights
-
Overhead distribution line staked in tandem with road widening construction
-
Navigated tight clearances with adjacent utilities
-
Overcame compacted terrain with creative fieldwork techniques
Coordinated Utility Staking for Capital Improvement Project Execution
The Challenge
Root Cause Analysis
- Multi-Utility Congestion: Numerous utilities operating in a shared corridor increased complexity.
- Terrain Obstruction: Hard-packed soil and construction activity impacted staking operations.
- Design Dependency: Staking needed to match CAD-based design layouts aligned with roadway improvements.
The Solution
Integrated Field Coordination
The team staked the proposed power line in coordination with AutoCAD references supplied by the utility coordinators, ensuring alignment with the revised road design and location of other underground and overhead utilities.On-Site Problem Solving
Where ground resistance made driving stakes difficult, the crew employed a railroad spike to break up the compacted soil; an efficient, field-based solution that enabled timely progress without compromising accuracy.Utility Awareness & Design Precision
The team’s attention to detail ensured the new pole locations avoided conflict zones while maintaining optimal clearances required by PEC and local regulations.Key Benefits
- Design Accuracy: Staking was executed exactly per project requirements.
- Time Savings: Field adaptability avoided delays stemming from external factors.
- Client Confidence: PEC benefited from consistent communication and reliable execution in a constrained environment.
- Safety & Coordination: Clearly defined boundaries helped prevent interference during and after construction.