Customer
Large IOU
Location
Zirconia, NC
Highlights
-
Restored power infrastructure in storm-damaged, high-risk terrain
-
Eliminated inaccessible transformer through innovative redesign
-
Replaced aging and damaged underground cable network
-
• Delivered project safely within 2 months despite environmental hazards
Distribution Project: Overcoming Terrain and Storm Damage with Smart Engineering
The Challenge
Root Cause Analysis
Severe weather-induced soil erosion led to the collapse of the supporting bank structure, exposing aging underground cables. Ground shifting further damaged existing infrastructure, increasing the risk of outages and safety incidents.The Solution
Key Benefits
- Improved Safety: Eliminated hazardous transformer access and reduced risk from exposed cables.
- Enhanced Reliability: Replaced aging and damaged primary cables to ensure stable power distribution.
- Optimized Design: Redesigned distribution layout to better suit challenging terrain conditions.
- Project Efficiency: Completed within 2 months despite environmental and logistical challenges.
- Collaborative Planning: On-site pre-construction coordination ensured alignment between client, engineers, and field teams.